Championship Course Update, Sept. 11

Mike Wilcox sends:

Here is the latest on the renovation progress.
All of the shaping, graveling and liner installation of bunkers is complete. Wadsworth Golf Construction is now in the process of hauling sand to each bunker. Once they finish, they will begin leveling it out.
The sod team also finished sodding the bunker surrounds today. They have now moved on to grassing and seeding other areas of the course.
Wadsworth Golf Construction still has several punch list items to knock out and areas to clean up, but we are on the “home stretch.”
Finally, the Tanglewood maintenance staff has aerated the Reynolds Course and overseeded the tees and fairways on both courses. Fall is near!
Cheers,
Mike